Public Notice on the Acceptance of Soil and Water Conservation Facilities for the Zhonghui New Energy 20 MW Photovoltaic Power Generation Project in Baqizhai, Tieling
Release date:
2018-04-17 00:00
Author:
In accordance with the requirements of the Ministry of Water Resources’ Notice on Strengthening Mid‑ and Post‑Project Supervision and Standardizing the Self‑Verification of Soil and Water Conservation Facilities for Production and Construction Projects (Shui Bao [2017] No. 365), an acceptance team was established, with our company serving as the team leader and the soil and water conservation plan preparation unit, the supervision unit, the monitoring unit, the construction unit, and a third‑party agency as members. The team independently organized the acceptance of the soil and water conservation facilities for the Zhonghui New Energy Tieling Baqizhai 20 MW Photovoltaic Power Generation Project. Following the project’s approval, our company commissioned the plan‑preparation unit to prepare the soil and water conservation plan report and obtained the corresponding approval document; it was determined…
In accordance with the requirements of the Ministry of Water Resources’ Notice on Strengthening Mid‑ and Post‑Project Supervision and Standardizing the Self‑Verification of Soil and Water Conservation Facilities for Production and Construction Projects (Shui Bao [2017] No. 365), an acceptance team was established, with our company serving as the team leader and comprising representatives from the soil and water conservation plan preparation unit, the supervision unit, the monitoring unit, the construction unit, and a third‑party agency. The team independently organized the acceptance inspection of the soil and water conservation facilities for the Zhonghui New Energy Tieling Baishizhai 20 MW Photovoltaic Power Generation Project.
Following the approval of the Zhonghui New Energy Tieling Baqizhai 20 MW Photovoltaic Power Generation Project, our company commissioned the project‑planning agency to prepare the Soil and Water Conservation Plan Report, which was subsequently approved. A specialized contractor for soil and water conservation was selected, and a qualified entity was engaged to provide supervision and monitoring throughout the construction phase. Upon completion of construction, a third‑party organization prepared the “Soil and Water Conservation Facilities Acceptance Report for the Zhonghui New Energy Tieling Baqizhai 20 MW Photovoltaic Power Generation Project.” An acceptance meeting was held on April 16, 2018. The acceptance committee confirmed that the reported data are accurate and valid, the construction quality meets the design specifications, and the project complies with the soil and water conservation acceptance criteria. Accordingly, the soil and water conservation facilities of the Zhonghui New Energy Tieling Baqizhai 20 MW Photovoltaic Power Generation Project are hereby approved as having passed acceptance.
This is hereby made public, with the public notice period running from April 17 to April 29. During this period, you may contact our company by telephone to report any issues or raise objections.
Attachment:
Acceptance and Appraisal Report
Phone: 0512-82355888
Tieling Zhonghui New Energy Co., Ltd.
April 17, 2018
Recent News
Leave a Message Online
If you have any questions about our products, please contact us promptly—we will be happy to assist you.